Wallted A/S has carried out deep compaction on an area of 13.500 cubic meters at Port of Frederician for the construction of eight grain silos and various buildings to be directly founded. The deep compaction is carried out with a PVE40VM vibrator and a tubular steel pile welded with vibrio wings, an equilateral triangle with a side length of two meters.